We are very happy to have reached another important milestone in the construction of the 197,000 m³ ethane tank for “Ineos Project One” in Antwerp. 🙌
The outer concrete wall of the tank has been completed on May 17th at 1 am.
Here are some facts about the sliding:
👉 Duration: 339 hours
👉 Concrete Volume: 9,740 m³
👉 Pumping Average Rate: 23,4 m³/h
👉 Average Speed of Sliding: 2,265 m/day
We thank the whole project team for their great work and thank Ineos Belgium for their trust placed in us! 👏👏
Project ONE, is a marquee project within our industry, being the largest petrochemical sector investment in Northern European market within the last 20 years.
By loading the video, you agree to YouTube's privacy policy.
Learn more
Privacy Statements - TGE Gas Engineering (tge-gas.com)