Successful cool down of Ethylene Storage Tank in our Project in Bangladesh

We are very delighted to announce that we have reached the key milestone for our Ethylene Terminal Project in Bangladesh! The storage tank had been successfully cooled down to the required -101 degrees, and the first Ethylene barge had been unloaded. The ethylene terminal has been successfully put into operation. The cryogenic ethylene storage plant imports “warm” […]

Meet us @ Gastech 05.- 08.09.22 in Milan!

We are absolutely pleased to announce our participation at this years Gastech, taking place 5th to 8th of September in Milan! You can find us @ the German Pavilion on stand 15F50!We are looking forward to meeting you there 🤝 www.gastechevent.com

Successful Roof Lifting in Huizhou, P.R. China

We are proud that we have reached another important milestone in our Huizhou LNG Terminal EPC Project. The roofs of two 200,000 m³ LNG tanks (Tank#1 & Tank#2) had been successfully lifted. We are very happy about the close and successful cooperation with our consortium partner CIMC EnTech and would like to thank the teams […]

Successful Roof Lifting in Poland

We are proud that we have reached another important milestone in our Świnoujście LNG terminal expansion project. The roof of the 180,000 m³ LNG tank had been successfully lifted. We are very happy about the close and successful cooperation with our consortium partner PORR Polska! Thanks for the professional work of PORR and TGE teams! 2022 06 […]

Come and visit us @ PRC Summit Helsinki

We are looking forward to our participation at this years PRC Summit in Helsinki, 30.-31. May 2022! Our team will be present with a stand and we hope to see there and at our presentation, Day 2 – Session 6 – Topic: “State of the Art Technologies for extended Plant Lifetime” to be held by […]

TGE as Platinum Sponsor at 4th Global LNG Forum

We are happy to participate as Platinum Sponsor at the 4th Global LNG Forum, 26th – 27th of April in Milan. Come and meet us on our stand and listen to our presentation “Accelerating permitting with TGE’s Reference Product Model for LNG Terminals”!

Smooth installation of Earth Covered Tanks

We are happy that we have reached another important step in our LNG/LPG conversion project. The installation of the Earth Covered Tanks ECTs went smoothly! The two tanks have a gross capacity of 400 m³ and 30 m length x 4.2 m diameter and 104 tons of empty weight. Thanks to the whole project team for their […]

Back-up Natural Gas Supply for the European Industry

Special situations require clever ideas to bridge short-term gas supply bottlenecks for the industry. We deliver such solutions for operation in next winter. Back-up plants with storage volumes of several hundreds of m³ LNG, or more, supply industrial customers with natural gas via the “Virtual Pipeline”. The TGE solutions allow the delivery of 30mill Nm³/a […]

TGE participates in VDMA press conference for large scale construction

We are happy to announce VDMAs online press conference for large scale plant construction, taking place on March 21st, 2022. The press conference is followed by several Break Out Sessions where Thomas Wehrheim will represent TGE as experts for Chemical Plant Construction. The audience of this press conference will be journalists, analysts, stakeholder from political […]